Mon Project


Project Description

Process Plus performed the conceptual engineering and limited detail design engineering for a project to limit toluene emissions below 10 tons per year for a chemical plant in northeastern Illinois. The customer was also interested in recovering as much solvent as possible, with a resultant reduction in raw material and / or overall operating costs, as a means of offsetting the investment expense related to executing the project.

System Includes

  • Vent Condensers
  • Glycol Chiller
  • Carbon Adsorption Canisters
  • Truck & Rail Car Loading / Unloading Connections for Vapor Recovery

Services Provided

  • Concept Development
  • Process Definition Engineering
  • Detail Design Engineering
  • Procurement Services
  • Expediting
  • Equipment Documentation
  • On-site Construction Management


Total Project Capital

$2.5 million

Start Date

February 2006 – August 2006 Conceptual Engineering & Design

September 2006 – February 2007 Procurement & Construction Support

Status

Operational February 2007